Cost database — material rates and labor units

AssemblyTradeUnitMaterial CostLabor Hours
Slab on grade, 4" w/ WWFconcretesf$3.200.05 hrs
Continuous footing, 18"×8"concretelf$28.500.35 hrs
Metal stud partition, 3-5/8" 20gaframinglf$4.800.12 hrs
LVL header, 3-1/2" × 11-7/8"framinglf$18.000.20 hrs
TPO membrane, 60mil, fully adheredroofingsf$2.950.04 hrs
Tapered EPS insulation, 4" avgroofingsf$1.800.02 hrs
Aluminum storefront, thermally brokenwindows doorssf$68.000.25 hrs
Hollow metal door & frame, 3'×7'windows doorsea$4802.0 hrs
5/8" Type X gypsum boardinteriorsf$0.680.015 hrs
ACT ceiling, 2×4 gridinteriorsf$2.400.02 hrs
LVT flooring, commercial gradefinishessf$4.500.03 hrs